Objectives This assignment has been designed so that you would be able tounderstand the concept of..

Objectives
This assignment has been designed so that you would be able tounderstand the concept of EVM (earnedvalue management). After doingthis assignment, you willbe having a good grasp onAnalysis of a project usingEVMFactors effecting EVM
Assignment
Consider the given table
Time%Complete
Expected
PV
AC%Complete
actual
EV1
15
70000
10
2
30
125000
20
3
55
110000
50
4
80
190000
75
5
100
220000
100
The table shows the following information regarding aparticular project
Time: in weeks
% completion (expected): Theexpected %completion of a project against the respectiveweek
PV: Planned value (inRs)
AC: Actual Cost (inRs)
% completion (actual): Theactual %completion of a project against the respectiveweek
PV: Earned value (inRs)
You are required to calculate PV andEV against each week. The PV andEV can be calculated asunder:
Planned Value:
PV= %complete (expected) * BAC
Earned Value:
EV= %complete (actual) * BAC
Where BAC is the budget aftercompletion which is 250000
Also analyze the projectperformance on weekly bases considering PV, AC,EV and % complete.