Determine the number of studs needed for a 120-foot- long wall where the studs are spaced at 16 inches on center.
Determine the number of 20-foot-long pieces of rebar needed to complete a 240-foot- long footing. The pieces are spliced with a lap of 18 inches and form a single bar running the length of the footing.
Determine the volume of a 20-foot by 15-foot by 4- foot-high concrete footing. Express your answer in cubic yards and include 5% waste.
An 8-foot-high by 50-foot-long wall is faced with 7 1/2- inch-long by 2 1/2-inch-high bricks. The mortar joints between the bricks are 1/2-inch thick. Using the area method, determine the number of bricks needed to face the wall.

How many cubic yards of concrete are required to construct a 75-foot-long by 24-inch- wide by 10-inch-thick continuous footing? Include 10% waste. Concrete must be ordered in quarter-yard increments. Determine the length of forms needed. The footing has three #4 continuous bars. The rebar is lapped 21 inches. Determine the number of 20-foot-long bars that needs to be ordered for the footing.
How many cubic yards of concrete are required to construct 5 each 24-inch by 12-inch by 8-foot-high concrete columns? Include 5% waste. Concrete must be ordered in quarter- yard increments. Determine the square footage of forms needed.
Set up Excel Quick Tip 5-1 (Spread Footing)
Set up Excel Quick Tip 5-2 (Rectangular Column) in excel

(DO NOT PLAGIARISM)The post Estimating and Cons Costs (DO NOT PLAGIARISM) first appeared on www.nursing-homeworks.com .Estimating and Cons Costs (DO NOT PLAGIARISM) was first posted on January 30, 2024 at 3:26 am.©2019 "www.nursing-homeworks.com ". Use of this feed is for personal non-commercial use only. If you are not reading this article in your feed reader, then the site is guilty of copyright infringement. Please contact me at [email protected]